The build process, stage by stage

Updated 2026-06-24 · Owner: Abraham · INTERNAL build playbook (1 of 4)
↖ Overview→ Cost & budget → Materials & finishes by tier → Architecture & permits → Contractor & team

A custom home in Panama runs 10 to 12 months from signed contract to keys for a single-story; 12 to 15 for a two-story or a difficult site. Below is the full sequence, with realistic durations, what share of the budget each stage consumes, who is on the hook, the buyer's touchpoint, and the mistakes that blow up timelines. Phases overlap in reality (permits run while design finishes; MEP overlaps structure), which is why the calendar is shorter than the sum of the stages.

Read this with the money in mind. The percentages below are share of the construction cost. They map to the milestone-payment schedule (see Contractor & Team). Sora's promise is a fixed turnkey price locked at contract, with payments released only against verified progress at each stage.
mo 048101214
Design + plans6–10 wk
Permits8–14 wk
Earthwork + foundation4–6 wk
Structure + roof12–16 wk
MEP rough-in6–8 wk
Finishes10–14 wk
Handover + keys2–4 wk
Typical durationSlack if delaysTypical delivery: 10–12 months

Phase 0 · Land & feasibility (before any contract)

This happens before the build clock starts, but it is where builds are won or lost. Titled land only. Confirm titled vs Rights of Possession (ROP), pull a fresh Public Registry certificate, get a survey, and check Paz y Salvo (tax clearance). Verify utilities at the lindero (water, power, road), slope, and access. A quick soil read and a feasibility budget against the model and tier set the fixed price. If the lot can't be built on sanely, this is where we say "not yet."

The seven build stages

1

Design + plans

6–10 weeks7–10% of cost
What happens
Who
Licensed architect (idóneo) + structural/electrical/sanitary engineers. Sora coordinates; buyer approves.
Buyer touchpoint
Concept review, one or two revision rounds, then sign-off on plans + finishes. After sign-off, changes become change orders.
Pitfall
Endless revisions. Lock the design. Every post-sign-off change costs time and money and is the #1 silent timeline killer.
2

Permits

8–14 weeks1–2% of cost
What happens
Who
The idóneo architect/engineer submits; Sora tracks. The buyer does nothing here except wait.
Pitfall
Coastal/ANATI files and rural municipalities move slowly and unpredictably. Build the slack in; never promise a ground-breaking date before permits are in hand.
3

Earthwork + foundation

4–6 weeks12–15% of cost
What happens
Who
GC + foreman (maestro de obra), excavation sub, the structural engineer signing off the pour.
Buyer touchpoint
First big milestone photo/video set. Slab poured = visible, fundable progress.
Pitfall
Skipping or rushing the soil study; pouring on poor fill. Foundation problems are the most expensive to fix later. This is where cheap builders cut.
4

Structure + roof

12–16 weeks30–35% of cost
What happens
Who
GC, masons, steel crew, roofers, the structural engineer.
Buyer touchpoint
The most satisfying stretch on video: the house takes its shape. Biggest single payment milestone.
Pitfall
The longest stage and where schedule slip accumulates. Weather (rainy season May–Nov), material lead times, and crew availability all bite here.
5

MEP rough-in (mechanical, electrical, plumbing)

6–8 weeks10–12% of cost
What happens
Who
Electrical and sanitary subs under the GC; the MEP engineers sign off before close-up.
Pitfall
Closing walls before inspection. Anything wrong here is buried behind finishes, so verify rough-in before plaster.
6

Finishes

10–14 weeks25–30% of cost
What happens
Who
Finish trades: tilers, carpenters, painters, kitchen/cabinet installers, pool sub, landscaper.
Buyer touchpoint
High-frequency updates; finish selections confirmed against the spec annex (no surprises if locked at Stage 1).
Pitfall
Imported finishes (Italian marble, high-end appliances) with long lead times that weren't ordered early. Order long-lead Firma items during Stage 4.
7

Handover + occupancy

2–4 weeks0–2% of cost
What happens
Who
GC clears punch list; Sora + buyer (or buyer's rep) do the final walk; municipality inspects.
Buyer touchpoint
Final walk-through (in person or by video), punch-list sign-off, then retainage released. Keys.
Pitfall
Releasing the final payment before the punch list is truly done. Hold retainage (5–10%) until it is.

Stage → payment milestone map

StageDuration% of costPayment trigger
Design + plans6–10 wk7–10%On signed plans (design fee)
Permits8–14 wk1–2%Permit lodged / approved
Earthwork + foundation4–6 wk12–15%Slab poured + engineer sign-off
Structure + roof12–16 wk30–35%Roof on / dried in
MEP rough-in6–8 wk10–12%Rough-in inspected
Finishes10–14 wk25–30%Finishes complete
Handover2–4 wk0–2% + retainagePunch list cleared + occupancy

Percentages are construction cost only (land, design/permit fees, and a ~5–10% retainage held to the end are handled separately). Always pay against verified progress, never ahead of it.